Implementation April 15, 2026 · 25 min read

Enterprise Deployment Checklist

Comprehensive planning guide for large-scale AUDITDEX rollouts covering SSO configuration, data migration, user provisioning, and change management.

Deployment Phases

A standard enterprise deployment runs across four phases over 6–12 weeks depending on scope. This checklist covers each phase with specific deliverables and success criteria.


Phase 1: Pre-Deployment (Weeks 1–2)

Technical Readiness

  • Confirm network connectivity to api.augixsys.com and app.augixsys.com (HTTPS/443 outbound)
  • Identify SSO provider (Okta, Azure AD, Google Workspace, ADFS)
  • Export existing control library from current system (CSV or Excel)
  • Document current evidence storage locations (SharePoint, shared drives, email)
  • Confirm data residency requirements (India, EU, US)

Organizational Readiness

  • Identify executive sponsor
  • Appoint AUDITDEX Platform Administrator (1–2 people)
  • Identify pilot team (5–10 users for initial rollout)
  • Schedule change management communications

Phase 2: Core Configuration (Weeks 3–4)

SSO Setup

  1. Log in to AUDITDEX as super-admin
  2. Navigate to Settings → Identity → SSO
  3. Select your provider and follow the provider-specific guide (linked in the UI)
  4. Test SSO login with a pilot user before proceeding
  5. Enable “SSO Required” to prevent password-based login after go-live

User Provisioning

AUDITDEX supports SCIM 2.0 for automated user provisioning from your identity provider. Configure SCIM before bulk user import to ensure ongoing synchronization.

User roles:

Role Capabilities
Super Admin Full platform access, billing, SSO
Platform Admin User management, template library, integrations
Engagement Lead Create and manage engagements, assign team
Auditor Execute testing, upload evidence, record findings
Reviewer Approve workpapers, publish reports
Read Only View engagements and reports, no write access

Control Library Import

Import your existing control library using the provided CSV template (download from Settings → Controls → Import Template). Required columns: control_id, title, description, framework, owner_email.


Phase 3: Pilot Rollout (Weeks 5–8)

Pilot Engagement

Configure one live engagement using the pilot team. Success criteria:

  • All team members can log in via SSO
  • Evidence collected through DRL for at least 10 controls
  • At least one finding raised and reviewed
  • Draft report generated from platform

Feedback Loop

Hold a structured retrospective with the pilot team at the end of Week 7. Capture:

  • What worked well
  • What was confusing
  • What was missing

Adjust configuration before broad rollout.


Phase 4: Full Rollout (Weeks 9–12)

Communication Plan

Audience Channel Message Timing
All audit staff Email + All-hands Platform launch, training dates Week 9
Evidence providers Email New portal for evidence submission Week 10
Audit committee Briefing New reporting capabilities Week 11
IT/Security Ticket API access for monitoring integrations Week 9

Training

AugIx provides live onboarding training for all user roles. Schedule sessions through your Customer Success Manager. Training materials (videos, quick-reference cards) are available in the Help Centre.

Go-Live Checklist

  • All users provisioned via SCIM
  • SSO Required enabled
  • Old evidence storage migrated or access removed
  • Monitoring integrations configured and tested
  • First production engagement created

Post-Deployment

Review the following 30 days after go-live:

  • Login success rate (target: >99%)
  • Evidence submission rate through portal vs. email (target: >90% through portal)
  • Control testing cycle time vs. baseline
  • Outstanding CAPA count vs. baseline

Your Customer Success Manager will conduct a formal 30-day review and provide a deployment health report.